# Q7A · Recommend a suitable mitigation measures that can be suitably adopted for capacity de…

Subject: Disaster Management

Exam: TEE

Reader: https://deep-learning-study-room.vercel.app/dm/#tee/papers/paper-2026-07-10/q7a

Canonical: https://deep-learning-study-room.vercel.app/read/dm/tee/papers/paper-2026-07-10--q7a/

Actual TEE paper · 100 marks · 3 hours · Q1 + any four of Q2–Q7

### Q7A. Recommend a suitable mitigation measures that can be suitably adopted for capacity development against cyclone. Justify and explain any such 4 measures in detail. [10 marks]

#### Answer

1. **Warning and last-mile communication.** Use official forecasts, clear action messages and several communication channels. A forecast must reach fishers, visitors and people without smartphones, with enough time and support to act.
2. **Shelters and evacuation access.** Provide accessible shelters outside surge and flood zones, linked by reliable routes. Practise transport, headcounts and support for people needing assistance so that shelter capacity becomes usable protection.
3. **Resilient buildings and lifelines.** Strengthen roof connections and protect power, water and communication systems to appropriate standards. Hospitals require backup services and protected equipment to keep functioning during response.
4. **Risk-informed coastal land use.** Use surge and flood maps to control exposed development and locate critical infrastructure safely. Protect mangroves and appropriate coastal vegetation as part of a wider protection system, not a guaranteed barrier against every surge.

These measures build information, physical, organisational and community capacity. They reduce losses; they do not prevent the atmospheric cyclone itself.

#### Real case · Phailin, 2013

India reported pre-emptive evacuation of more than one million people before Cyclone Phailin. This is a real example of warning linked to action. For a formation question, keep the physical process separate; for management, explain how evacuation reduces exposed people’s immediate risk.

[Case reference ↗](https://www.pib.gov.in/newsite/erelcontent.aspx?lang=2&reg=48&relid=105888)