Disaster Management · TEE · practice
Two additional authored calculation exercises
Optional calculation practice
Supplementary worked examples · no numerical question found in the available 12 TEE sittings
Added runoff and magnitude exercises. Their numbers and question selection were written for practice; this is not a recovered paper or a confirmed M2/TEE composition.
Illustrative calculation (not a PYQ). A catchment has C = 0.6, I = 50 mm/h and area = 0.5 km². Estimate peak runoff in m³/s using the rational method.
Answer
Given
| Given | Value |
|---|---|
| Runoff coefficient C | 0.6 |
| Rainfall intensity I | 50 mm/h |
| Catchment area A | 0.5 km² |
To find
Estimated peak runoff Q in m³/s.
Formula and why
Q=0.27778CIAThe factor converts mm/h over km² to m³/s. Assume the rainfall intensity and catchment meet the rational-method assumptions.
Step-by-step solution
Step 1. Multiply coefficient and intensity
0.6\times50=30Step 2. Multiply by catchment area
30\times0.5=15Step 3. Convert to discharge
Q\approx0.27778\times15=4.1667\,\mathrm{m^3/s}Final answer: Approximately 4.17 m³/s.
Illustrative calculation (not a PYQ). Two earthquakes have magnitudes 6 and 5. Find the amplitude ratio and approximate energy ratio.
Answer
Given
| Quantity | Value |
|---|---|
| Larger magnitude | 6 |
| Smaller magnitude | 5 |
To find
Larger-to-smaller amplitude and energy ratios.
Formula and why
A_2/A_1=10^{\Delta M},\qquad E_2/E_1\approx10^{1.5\Delta M}Magnitude is logarithmic. The energy relation has a different exponent from the amplitude relation.
Step-by-step solution
Step 1. Calculate magnitude difference
\Delta M=6-5=1Step 2. Calculate amplitude ratio
10^1=10Step 3. Calculate energy ratio
10^{1.5\times1}=10^{1.5}\approx31.62Final answer: Amplitude ratio 10:1; approximate energy ratio 31.62:1.